18 September 2014

Construction Notes

The installation of the new roofing system is nearly complete at this time.  Only trim work remains, and the manufacturer’s representative is scheduled to visit the site in the coming weeks to perform a final inspection of the work.  Once the final inspection has passed, then the 20 year warranty period will begin for the new roofing system.  The roofing work at the school will be complete by the end of this month.   As of October 1st only some parking lot restoration work may remain, as related to the roofing work.

The installation of the windows is also nearly complete.  Next week the contractor will finish installing the glass in the multipurpose room, and finish installation of remaining window trim in all areas.  The remaining window caulking work is expected to be completed the week of 9/29.  All window work at the school is expected to be complete by the end of this month, with only some punchlist work remaining after that.

The new VCT work at the Cafeteria is complete at this time.

The sound attenuation work at the Learning Curve area is complete at this time.

Exterior masonry restoration work at the school in various areas is complete at this time.

The installations of the new exterior soffits are nearly complete with minor painting work remaining.


Work installing a new generator located at the building exterior, is scheduled to begin in the coming weeks, to be completed this fall.  This work will be coordinated with the District so that there are no disruptions to student instruction. 