06 October 2014

Construction Updates

The installation of the new roofing system is substantially complete at this time, and the manufacturer’s representative is scheduled to visit the site during the first week of October to perform a final inspection.  Once the final inspection has passed, then the warranty period will begin for the new roofing system.  As of next week, only some parking lot restoration and minor punchlist work may remain, as related to the roofing work.

The installation of the windows is substantially complete including all window caulking work.  Installation of new windows treatments throughout the school is complete.  There is an on site meeting with the architect, construction manager, and the District scheduled for Thursday 10/9 to perform a punchlist inspection on the windows.

The new VCT work at the Cafeteria is complete at this time.

The sound attenuation work at the Learning Curve area is complete at this time.

Exterior masonry restoration work at the school in various areas is complete at this time.

The installations of the new exterior soffits are nearly complete at this time, with only some painting work remaining, which is to be completed in the coming weeks.


Work installing a new generator located at the building exterior, is scheduled to begin in the coming weeks, to be completed this fall.  This work will be coordinated with the District so that there are no disruptions to student instruction.